MWO 9 -2330-390-35-1
REQUIREMENTS
DESCRIPTION
WORK FORCE/SKILLS
MAN -HOURS
Detaching Front and Rear Dollies
Operational
0.5
Removal of Structural Frame Sections
*Front
Operational / Mechanic
2.0
*Rear
Operational / Mecha nic
2.0
Removal of Vertical Positioning Tubes
* Front
Cutting
1.0
* Rear
Cutting
1.0
Preparation Bottom Beam
* Front
Grinding / Welding / Painting
2.5
* Rear
Grinding / Welding / Painting
2.5
Preparation Top Beam
* Front
Grinding / Welding / Painting
3.5
* Rear
Grinding / Welding / Painting
3.5
Assembly of Modified Frame Sections
* Front
Operational / Mechanic
2.0
* Rear
Operational / Mechanic
2.0
Installation of Structural Frame Sections
* Front
Operational / Mechanic
3.0
* Rear
Operational / Mechanic
3.0
Placing Dolly into Transport or Travel Mode
Operational
0.5
Total man-hours required for a single application of this MWO
29.0
7. TECHNICAL PUBLICATIONS AFFECTED/CHANGED AS A RESULT OF
THIS MWO.
Technical Publication
Date
TM 9-2330-390-14&P C4
01 Nov 00
AWS 2.4-Standard Symbols for Welding, Brazing,
and Non-destructive Examination
AWS 3.0-Terms and Definitions
AWS D1.1- Structural Steel Welding Code
MIL-C-53072B
8. MWO KITS, PARTS AND THEIR DISPOSITION.
a. The following kit is required to accomplish this modification. The security
classification of this kit is unclassified. Shipping data is: weight 452.2 lbs;
NOMENCLATURE
NSN
CAGEC
PART
Pos itioning Tube Reinforcement Kit
19207
57K4484
3