REQUIREMENTS
WORK FORCE/SKILLS
MAN-HOURS
Wheeled vehicle mechanic
1.8
(MOS 63B) or equivalent
Total man-hours required for a single application of this MWO are 1.8 hours.
WARNING
MWO 9-2330-392-35-1, STEEL DRAW BAR must be installed prior to
replacing the rivets with bolts. Failure to follow this warning will result in
catastrophic failure of the aluminum drawbar leading to equipment damage and
possible injury or death of personnel.
d.
MWOs To Be Applied Prior to or Concurrently with this MWO. Installers
will verify MWO 9-2330-392-35-1, Steel Draw Bar and MWO 9-2330-392-
20-1, Surge Brake Actuator has been applied.
e.
Additional Information. Not Applicable.
7.
TECHNICAL PUBLICATIONS AFFECTED/CHANGED.
TM 9-2330-392-14&P, 1 October 1995, with change 1, 13 March 1998 and
Change 2, 27 April 2002.
8.
MWO KIT/PARTS AND THEIR DISTRIBUTION
a. Kit Needed to Apply MWO.
This MWO kit consists of standard Grade 8 nuts and bolts available through the
Defense Logistic Agency supply system. It is not economically feasible to assemble
a kit for distribution, therefore, units should order parts needed to apply this MWO as
described in paragraph b below. Reimbursement for parts can be coordinated through
your MWO coordinator to TACOM, AMSTA-LC-CIPWM, Mike Dargis, DSN 786-
7391, commercial (586) 574-7391, e-mail: dargism@tacom.army.mil.
b. Contents of MWO Kit:
The table below reflects parts required to modify one trailer. Note that unit of issue for
some items listed are sold in packages of 50 or 100 only. Units should use caution
when ordering to insure they order the correct quantities.