HYDRAULIC LINES
TB 5-2520-551-24
NOTE
Refer to figure 5 for hydraulic line installation. Observe line
tags for proper installation while connecting hydraulic lines.
182. In truck bed, place sense, A/C high pressure, and generator high pressure
hydraulic lines through holes in truck bed floor. Secure hydraulic lines
in clamps on forward tiedown crossmember in accordance with figure 4.
183. Install second plate (item 14, C5122613-1) in truck bed and secure with six
bolts (item 37, MS90725-8), flat (item 45, AN960C416) and lock washers
184. Under truck bed, secure hydraulic lines in clamps on forward crossmember in
accordance with figure 4.
185. Position protective sleeve (item 56, C5131118-3) over generator pump low
pressure return line (item 107, C5111OO9-1). Slide sleeve up hose, until
top of sleeve is positioned just below channel bracket (item 6,
C5110651-1). Trim sleeve as necessary. Using 1/4" flat tip screwdriver,
tighten hose clamp (item 60, AN737TW58) securing protective sleeve (item
56, C5131118-3).
50