4-10. GENERAL
The full CPP inspection consists of three levels of inspection: Level I, Level II, and Level III. Level I is essentially a visual
conformance check from 50 feet or more. Level II is a close-up boundary inspection using a CPP overspray gauge. Level
III is a detailed comparison of actual physical measurements to nominal dimensions.
4-11. MATERIALS/TOOLS REQUIRED
After becoming completely familiar with the inspection procedures outlined below, the inspector should assemble the
following materials/tools:
CPP designs, including inspection worksheet (para 4-3) and overspray gauge (fig 4-3)
One (1) 6-foot steel measuring tape, graduated in sixteenths (or thirty-seconds) of an inch
One (1) 6-foot steel measuring tape, graduated in tenths of an inch
Small T-square and/or straight edge
Soapstone or chalk
Pen, pencils, colored pencils
Paper/notebook
One plumb bob, with string